eaufort should be complete by mid-2014.But the works have not been all smooth sailing, with a 2.9km stretch of road east of Beaufort requiring rectification works after a temporary seal laid last June didn???t hold.Forty-seven property owners have also lost part of their land, including four who lost homes.Director of the Western Highway Project Mick McCarthy said progress was ???going very well??